CMS were appointed as Project Managers and Quantity Surveyors for the procurement of the Design Team and subsequent award of the contract to Integral Build. CMS were also involved in the procurement of other specialist consultants for both Architectural, Mechanical and Structural Engineering services which were provided by Stride Treglown, Jones King and Jenkins & Potter respectively.

The works consist of the formation of the library within the existing light well and extensive remodelling of the dining/ conservatory facilities, along with the main entrance and reception area. Specific changes for the project were the vast implementation of the works to minimise the disruption to the school’s activities, whilst the building remained occupied throughout. In addition there were significant refurbishment works to the existing dining hall, servery and ancillary rooms to form a lighter and better equipped dining area.